Prefab vs traditional

Prefab versus traditional dormer: the trade-off

This is your first real decision: have the dormer built in a factory and installed in one day (prefab), or built on site traditionally (3-5 days)? Prefab is cheaper and faster (€5,500-€8,500 for 3 m in 2026); traditional offers more customisation, potentially higher detail-level quality and is required in some aesthetics contexts (€7,500-€12,500 for 3 m). Prefab market share grows from 60% (2020) to 75% (2026); the quality gap has largely closed in 10 years.

Price prefab 3 m
€5,500 – €8,500
Price traditional 3 m
€7,500 – €12,500
Install time prefab
1 day
Install time traditional
3 – 5 days
Prefab market share 2026
~75%
Quote-to-handover prefab
3 – 6 weeks
Quote-to-handover traditional
8 – 14 weeks

Install pace and logistics compared

Prefab: prep (remove old tiles, open subframe) in the morning, hoist 11-13h with truck-loader or mobile crane, seal and lead/zinc in the afternoon. One day total; house remains habitable overnight. No temporary cover needed, no rain-ingress risk.

Traditional: roof open for 3-5 days. Each workday covered with scaffold sheeting and building film, but rainfall (Dutch autumn/winter) creates real moisture-damage risk to bedrooms below. Ask the contractor for insurance certificate for damage liability.

Logistics: prefab needs crane setup (1 day, €280-€900 depending on district), parking permit and street closure. Traditional needs scaffold (3-5 days, €450-€1,200), material storage in garden or street. Both require coordination with neighbours and municipality.

Price difference: what you get for it

Prefab is €1,500-€3,500 cheaper at equal size and finish. The difference is standardised production (CNC sawing, line assembly), shorter on-site labour and smaller execution risks. For a standard 3 m PVC dormer on a terraced house: €5,800-€7,500 prefab vs €8,000-€11,000 traditional.

You trade 'cheaper and faster' for 'less custom and more standard look'. Prefab works in 10-20 cm size steps, standard colours (RAL 9010 white, 7016 anthracite, 9001 cream, few variants) and standard frame layout. Intermediate sizes or non-standard colour: surcharge €450-€1,500.

For most terraced and simple houses prefab is excellent. Modern prefab quality (KOMO-PVC with heat-block, Rc ≥ 4.7, HR++ glass) has improved enormously in 10 years. For architecture with character, non-rectangular geometry or heavy-aesthetics locations: traditional.

Situations that require traditional

Monuments and protected village views where aesthetics requires specific detailing (brick cheeks, ornaments, non-standard frame layout). A dormer in Amsterdam centre, The Hague Statenkwartier or Den Bosch centre is almost always traditional — surcharge €3,500-€7,500 over prefab.

Dormers with non-rectangular geometry: balcony, curved roofline, asymmetric shape, integrated rooflight in front face. Prefab factories work with straight shapes; deviant geometry requires on-site custom.

Very wide dormers (> 5 m) or very tall (> 2 m front frame): prefab elements get too heavy (> 1,500 kg) and unwieldy for crane logistics. Traditional builds modularly from the sides inward. Houses with extreme roof pitch (< 25° or > 65°) also require on-site custom.

Quality and warranty compared

Prefab benefits from factory control: every production step measured and documented. Standard warranties: 10-15 years material, 5-10 years installation. KOMO certificate gives auditable spec. Modern prefab complaints centre on installation (poor sealant finish, lead joint not flat) — not the element itself.

Traditional depends heavily on the contractor. A craftsman delivers superior quality with details no factory can match (folded zinc, brick cheeks, inset awning). An average contractor takes 5 days to deliver something comparable to prefab — just more expensive and riskier (weather, lead time).

Risk: in traditional work 'standard' doesn't exist. Always request 3 quotes on identical specs (Rc-value, glass spec, material, frame layout, colour, sealant type). Demand a handover report with photo documentation. Request at least 2 references from projects 5+ years old.

FAQ

Is prefab always lower quality?
No, often more consistent. Factory production removes weather dependency and human variation. 'Lower quality' experiences usually trace to thin cheek cladding or cheap frames — not the prefab principle.
Can prefab come in any colour and size?
No, factories work in 10-20 cm steps and standard colours. Intermediate sizes or non-standard colours mean surcharges €450-€1,500 or switching to traditional.
When is traditional required?
Monuments, protected cityscapes with specific aesthetics requirements, non-rectangular geometry (balcony, curved roofline), dormers > 5 m wide or > 2 m tall, roof pitch < 25° or > 65°.
How long does each option take?
Prefab: quote-to-handover 3-6 weeks, install 1 day. Traditional: quote-to-handover 8-14 weeks, install 3-5 days. Add 6-10 weeks for permit-bound installs.
What do you recommend in 2026 for a terraced house?
For a standard terraced house in a modern district: prefab with KOMO-PVC, Rc ≥ 4.7, HR++ glass, 3 m. €5,800-€7,500 including install. For heavy-aesthetics districts or special architecture: traditional or hybrid with timber cladding.