One-day install

Dormer in one day: how realistic

'Installed in one day' marketing is largely true — but only for prefab PVC dormers up to 4 m, in good weather, with good crane access. Interior finishing often takes 1-3 extra days not included in that 'one day'.

Realistic for
Prefab PVC up to 4 m, clear crane pitch
Not 1 day for
Traditional, >4 m, complex roofs, bad weather
Interior extra
1-3 days after install
Crane on site
4-6 hours (€800-€1,500)
Success rate
85% with prepared prefab

What fits in that one day

Factory assembly of the prefab happens weeks before your install date (3-6 weeks production). On install day: delivery on low-loader, hoisting with telescopic crane, placement onto the opening, lead and zinc junction, exterior sealing.

Then tile repair around the cheeks, rainwater downpipe hookup, and basic cleanup. By 17:00-18:00 exterior work is done and your roof is watertight again.

What's NOT in that one day

Interior finishing (plaster, paint, floor join) — 1-3 extra workdays, often spread over 1-2 weeks for sealant/glue curing.

Permit procedure (8-26 weeks ahead), removing the old dormer on replacement (half to full extra day), and municipal inspection if required. For optional shading, blackout or special glazing: separate fitter appointment.

When one day is not realistic

Traditional timber (4-6 days build), dormers wider than 4 m (often two prefab segments, +1 day), complex roofs (composite, corner houses with double pitch).

Weather risk (rain, wind >6 Bft, frost <0°C), or when the crane must stand more than 12 m from the roof and no larger 60-80 t fits in your street.

Conditions for a successful 1-day install

Crane pitch within 10 m of the roof clear of obstacles (cars, trees, power lines), parking permit or restriction arranged 1-2 weeks ahead, and neighbours informed.

House access (key or person present) from 06:30 to 18:00, and at least 80 cm clear passage for material to the loft. Power and water for the crew. Without these the success rate drops from 85% to 50-60%.

FAQ

Can a 5-metre dormer be done in one day?
Sometimes, if delivered in one prefab piece (rare — most makers go up to 4.5 m in one piece). Two pieces: 1.5-2 days.
What does the 'one day' guarantee cost?
No premium vs standard prefab; crane hire (€800-€1,500) is in the package price.
Does the warranty hold on one-day install?
Yes. 10-20 year warranty identical to traditional.
What if the crane is delayed?
Good providers reschedule at no cost. Ask explicitly in the contract.
Can shading be fitted the same day?
Sometimes, if it's the standard package. Often 1-2 weeks later via a separate fitter (€150-€300 fitting).